Commercial management for a prime residential conversion with evolving scope and programme pressure.
Scope and programme moved throughout delivery, and the commercial position needed rebuilding to keep pace with the changes rather than being reconciled after the event.
As commercial manager we took direct responsibility for the site's quantity surveyors, negotiated variations as they arose, and secured the extensions of time the delay events actually supported, including the preliminary costs that followed from them.
Over £500,000 in variations negotiated, three extensions of time secured with associated preliminary costs recovered, and the final account moved from £2.84m to £3.02m on a properly substantiated basis.
This appointment falls under our contractor commercial support work.